The Woodruff Road Fix Is a Second Road, and Part of It Is Already Open

November 5, 2026

Behind the Woodruff Road storefronts near Verdae Boulevard, a short divided road runs through three roundabouts, at Verdae, Green Heron Road and Ketron Court, and ends at Woodruff Industrial Lane, with a 10-foot path alongside it. It opened in 2019 as the Parallel Parkway. SCDOT now calls it the Woodruff Road Bypass, and it's the starting piece of the largest road project in the region. In October, the Greenville News reported that the full project now has a start date.

Relief comes from a second road

SCDOT's plan builds a separate road. The preferred alternative is a new limited-access route parallel to Woodruff that runs from Verdae Boulevard to Smith Hines Road, where it meets Woodruff. It will have four travel lanes with a median, curb and gutter, and new bridges over both I-85 and I-385. The project FAQ lists a 5-foot sidewalk on one side, a 10-foot multiuse path on the other, roundabouts at several intersections, and a signal where the new route joins Woodruff. The bypass will cross over I-85 and I-385 but won't change those interstates. Changes at the Woodruff Road and I-85 interchange belong to a separate effort, the I-85/I-385 Gateway Project.

The project is aimed at a specific problem. SCDOT says the busiest section, from Roper Mountain Road to I-85, carries more than 40,000 vehicles a day at peak times. Because the corridor is so commercial, the midday rush is sometimes heavier than the evening one. A new road can't fix a lunchtime jam by widening the street the shops sit on. It can only give through traffic another way past them, along with improvements SCDOT plans for intersections and side roads on Woodruff itself.

The first stretch has been open since summer 2019, when the Greenville News reported the first half-mile in use. During the 2022 holiday shopping season, WYFF reported that police message boards were steering drivers onto Parallel Parkway as an alternative to Woodruff. The full project extends that segment all the way to Smith Hines Road.

The calendar, as it stands this fall

The project has been in the works for more than a decade. SCDOT started environmental work and public outreach in 2017, held a public information meeting on November 9, 2017, signed the environmental assessment in April 2020 and listed right-of-way acquisition for spring 2023. The next steps are below.

Milestone Current target Source
Phase 1 bids advertised: clearing, grubbing, demolition Spring 2027 Greenville News, SCDOT
Phase 1 work begins Summer 2027, about 18 months Greenville News
Phase 2: construction of the parallel route Fall 2029 SCDOT project page
First sections could open 2032 GPATS, via Greenville News
Substantial completion 2033 GPATS, via Greenville News
Final construction, per GPATS budget minutes 2034 GPATS, August 2026

Phase 1 is site preparation. If it starts in summer 2027 and runs about 18 months, that work wraps up around the end of 2028, ahead of the fall 2029 road construction on SCDOT's schedule. The 2033 date in the Greenville News and the 2034 date in the minutes of the Greenville-Pickens Area Transportation Study, or GPATS, track different milestones. The first is when the road should be substantially usable. The second is the last construction year in the funding schedule.

Why the start date moved up, and what the region gave up for it

Inflation is the reason. According to GPATS, the cost has more than doubled since the project got funding in 2020, rising from $130 million to an estimated $277 million. SCDOT proposed spreading the funding out over more years. Keith Brockington, GPATS transportation manager, told the Greenville News that waiting would have added about another $30 million in inflation alone. "By moving the project forward sooner, we're able to keep the inflation for the construction to a minimum," he said.

To move it up, the GPATS policy committee voted in August 2026 to delay other projects. The minutes record an 11 to 3 vote with one abstention and $28.409 million set aside for clearing and grubbing in fiscal year 2027. The Greenville News reported that documents from an October 12 GPATS meeting show at least nine corridor projects, six intersection projects and two pedestrian projects affected. Brockington said many of them likely won't see money again until 2033.

One of the delayed projects matters to anyone who rides south of the Eastside. The Mauldin Golden Strip Gateway, which would carry the Swamp Rabbit Trail into downtown Mauldin, isn't expected to start preliminary engineering until 2028.

Greenville County Council Chairman Benton Blount told the paper that Woodruff Road congestion is one of the top complaints he hears. He also said he doesn't like putting off other projects, "but I do understand the necessity to prioritize it (Woodruff Road), if nothing else simply because every year we wait the price seems to go up, and not just a little bit."

Haywood and Pelham kept their place in line

Some projects closer to home kept moving. Projects that had already started preliminary engineering were protected, the Greenville News reported, including East Butler Road, the Rutherford Road and North Pleasantburg Drive intersection, and the Haywood Road and Pelham Road intersection.

That intersection is the one Eastside drivers pass through to reach Haywood Mall and the shopping centers along Haywood. The GPATS project page lists the scope as:

  • Driveway consolidation
  • Signage and turn-lane improvements
  • Multimodal considerations
  • A final report recommending a Continuous Flow Intersection
  • Phase budgets of $250,000 for planning, $1 million for preliminary engineering, $4 million for right-of-way and $4.5 million for construction

The page says the scope will be reviewed with the City of Greenville. The August 2026 committee minutes describe the project as pending funding discussions, with the revised scope still to be worked out. No construction date has been published yet.

What the finished road is designed to deliver

The planners' own forecast gives the clearest picture of the outcome. Brockington told the Greenville News that SCDOT studies show Woodruff Road traffic in 2040 will look similar to what it was in 2013.

"Certainly not free-flow traffic, we'll never be able to get to that, but with the growth that Greenville sees, being able to maintain Woodruff Road traffic at a 2013 level is the best that we can expect."

The parkway is designed to hold the corridor near its 2013 traffic level while the area keeps growing. The Verdae end of the route already shows what the finished road will offer: a divided road behind the stores, roundabouts in place of signals, and a path wide enough for a bike. SCDOT posted its final design display on the project page this October. Questions go to project manager Megan Groves at [email protected].

Over the next few years, the Woodruff corridor will look very different, with clearing in 2027, bridges going up over the interstates later in the decade, and a new intersection design at Haywood and Pelham. If you'd like to talk through how these timelines line up with your own plans on the Eastside, David Dunford is happy to walk through the details with you. Let's Connect.